The Plan

Key Messages

• We Can Do It — We've Done Our Homework

• 3-Phase Plan — Phase 1: Safe to Open by Thanksgiving

• Future — Maintenance, Improvement, and Replacement

Summary To Date

• Built in 1985

• Minimal maintenance, if any

• Closed Spring of 1999

• Safety Audit, Summer of 2000

• Group formed to reopen playground, 9/21/00

• Proposal for Reopening, 10/3/00

Safety Audit

• No significant structural defects

• Maintenance Issues:

- wear and tear

- weathering

• Many safety issues, all can be accomplished

- most bring structure to guidelines that did not exist in 1985

- clear directions for repair/adjustments

Proposal

Three-phase plan:

  1. Safety First, reopen
  2. Continue Maintenance
  3. Improve and Plan Future

Phase 1: Safety First, Reopen

• Address all Safety issues in Safety Audit #1-3 and some #4

- key items are subsurface cushioning, entrapment/entanglement areas

• Repair broken apparatus

- ex. Suspension bridge, swinging platform, horse

• Remove three-four pieces that are not cost effective to make safe:
- tire cubes, tot slide and tire chains and nets

Phase 2: Continue Maintenance

• More #4s (mostly guardrail height extension)

• More board replacement

• Retrofit and reopen swing areas

• Begin thorough inspection plan and routine repair

Phase 3: Improve and Plan Future (Summer/Fall 01)

• More board replacement

• Additional sealer coat, as needed

• Inspection

• Assessment of life expectancy

• Initiate plan for replacement (TM 2002)

• Parking lot expansion/relocation

Funding

Our budget analysis for repairs and maintenance is:

Phase 1: $12,000

Phase 2: 4,000

Phase 3: 2,000

TOTAL: $18,000

We understand there is $4,000 or more in a town budget that is earmarked exclusively for this playground — the money raised by the original community group. This is the balance of approx. $7,500 less the $3,000 for the safety audit.

Our fundraising plan is to immediately solicit donations and to sell engraved bricks and boards plus T-shirts and sweatshirts, and possibly professional photo portrait packages.

We think the following is attainable

Current Balance for Park $ 4,000

Donations: 7,000

T-shirt/sweatshirts: 2,500

Brick/Board sales: 3,000

Photo sales: 2,000

TOTAL: $18,500

 

What We Need Tonight:

• Commission approval to proceed

• Recreation/Highway agreement to provide limited manpower, machines, trucks, disposal, as available

• Agreement on repair schedule and level to meet safety guidelines

• Minimal ongoing weekly maintenance by Rec. Dept. as with other parks (rake chips, cut grass)

• Agreement to call us immediately with any report of broken apparatus, etc.

• Regular report schedule to P&R Commission; semi-annual review/discussion